2 issues in taxes budget with critical priority
Measure FP general obligation bond issuance
The council hired Swinerton Builders and LPA Design to design the new Fire Stations 1 and 2 and police facilities paid for by the $93.35 million bond voters approved in 2024. Design runs through 2026; construction starts 2027 with fire stations done by fall 2028 and police by fall 2029. A five-person citizens oversight committee is coming.
Capital Improvement Program Process
The Commission was asked to confirm the city's six-year infrastructure spending plan matches the adopted General Plan — a required legal step before those projects move ahead.