Summary

The council hired Swinerton Builders and LPA Design to design the new Fire Stations 1 and 2 and police facilities paid for by the $93.35 million bond voters approved in 2024. Design runs through 2026; construction starts 2027 with fire stations done by fall 2028 and police by fall 2029. A five-person citizens oversight committee is coming.

At a glance

Total mentions
5
Last 30 days
2

Discussed at 2 meetings in the last 60 days; most recently Oct 13, 2026.

Impact analysis

💰Financial impact

About $3.57 million in design-phase contracts now, with construction costs locked by a guaranteed maximum price later.

✅Who benefits

Residents get modern, seismically sound fire and police facilities — and first responders get buildings designed around how they actually work.

⚠️Who could be affected

Property owners bear an additional property tax levy through 2056.

Mentions & discussions (5)

MeetingOct 13, 2026approved

City Council — October 13, 2026

The council approved selling up to $93.35 million in voter-approved bonds to rebuild Fire Stations 1 and 2 and the main police station. A AA+ credit rating means lower borrowing costs; property owners will pay an estimated $17.40 per $100,000 of assessed value starting November 2027.

MeetingOct 8, 2026approved

Budget & Finance Commission — October 8, 2026

The city is about to borrow $93.35 million to rebuild two fire stations and the police headquarters/annex. Estimated cost: 5.19% interest, about $17.40 per year per $100,000 of your home's assessed value — basically what was promised on the ballot. Council votes on the sale October 13.

MeetingAug 18, 2026approved

City Council — August 18, 2026

The $93.35 million bond for fire stations and the police station now gets a five-person citizen committee to verify the money is spent as promised. Applications open in fall 2026.

MeetingJul 7, 2026

City Council — July 7, 2026

The council hired Swinerton Builders and LPA Design to design the new Fire Stations 1 and 2 and police facilities paid for by the $93.35 million bond voters approved in 2024. Design runs through 2026; construction starts 2027 with fire stations done by fall 2028 and police by fall 2029. A five-person citizens oversight committee is coming.

MeetingJan 20, 2026

City Council — January 20, 2026

The city is moving forward with rebuilding fire stations and the police headquarters using Measure FP funds, hiring Griffin Structures to manage the process.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Redondo Beach

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.