SR46 Improvement Project construction impacts
Summary
Caltrans is building a roundabout at SR43/46, replacing the BNSF rail bridge, and adding bike lanes and ADA upgrades. Construction starts November 2026 and finishes October 2029, with night lane closures and some full closures of 46 at F and J Streets. Residents and businesses should expect disruption and watch for commuter alerts.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 3, 2026.
Impact analysis
Construction capital is $70.2 million, funded through Caltrans.
Drivers, freight, pedestrians and cyclists get a safer, smoother Highway 46 corridor — plus potential new businesses drawn by improved access.
During construction, drivers and F and J Street businesses face temporary closures and detours.
Mentions & discussions (2)
City Council - Nov 3, 2026
The $425,500 J.L. Plank contract for the HWY 46 crossing was pulled from the consent calendar as a duplicate, so it was NOT approved Tuesday. Watch for it to come back on a future agenda.
City Council - Jul 21, 2026
Caltrans is building a roundabout at SR43/46, replacing the BNSF rail bridge, and adding bike lanes and ADA upgrades. Construction starts November 2026 and finishes October 2029, with night lane closures and some full closures of 46 at F and J Streets. Residents and businesses should expect disruption and watch for commuter alerts.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Wasco
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.