High PriorityRoadsopen

FY 2026-27 road repair and rehabilitation project list

Summary

Supervisors want to put roughly $3 million of the budget contingencies toward paving interior neighborhood roads, split among the five districts, with possible sheriff work crews for brushing. Final numbers come back September 22.

At a glance

Total mentions
6
Last 30 days
1

Discussed at 2 meetings in the last 60 days; most recently Nov 3, 2026.

Impact analysis

💰Financial impact

About $3 million of contingency funds earmarked for district road projects.

✅Who benefits

Residents on neglected neighborhood roads in all five districts.

Mentions & discussions (6)

MeetingNov 3, 2026discussed

Board of Supervisors - Nov 3, 2026

Supervisor Kirk announced five town halls November 10-17 where District 3 residents can rank which roads get a share of $600,000 in asphalt funding — some roads in his district have pavement indexes of zero.

MeetingSep 15, 2026

Board of Supervisors - Sep 15, 2026

Supervisors want to put roughly $3 million of the budget contingencies toward paving interior neighborhood roads, split among the five districts, with possible sheriff work crews for brushing. Final numbers come back September 22.

MeetingAug 11, 2026

Board of Supervisors - Aug 11, 2026

Supervisors want $770,000 in excess contingencies directed to local neighborhood roads — the ones 'almost back to gravel' — possibly split by district. Public works is training crews on new paving and chip-seal machines, costing $160,000–$200,000 per mile so far.

MeetingJun 30, 2026

Board of Supervisors - Jun 30, 2026

The budget doubles the extra roads transfer to $1.5 million total, funding two road crew positions, materials and equipment. Hunts Road is already freshly paved, with more sections planned under state code limits.

MeetingJun 16, 2026

Board of Supervisors - Jun 16, 2026

The Board was scheduled to adopt a new project list for spending state gas tax money (SB 1 Road Maintenance and Rehabilitation Account) on local roads in FY 2026-27. This determines which Tuolumne County roads get repaved or repaired this fiscal year.

MeetingJun 2, 2026

Board of Supervisors - Jun 2, 2026

The county was scheduled to approve roughly $822,000 in combined contract increases with MGE Engineering for designing replacements of two aging bridges — Curtis Creek on Old Wards Ferry Road and Algerine Creek on Algerine Road.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Tuolumne County

What the council decided, in plain English — one email a week.