Tehama Asphalt agreement
Summary not yet generated for this topic.
Community sentiment
At a glance
- Public comments
- 3
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 29, 2026.
Public comments (3)
The Tehama Asphalt representative explained he has ~$10,000 of his own money into permits and engineering, that extraction costs roughly $150,000 in year one, and that a one-year deal would not be profitable for him.
Board of Supervisors — September 29, 2026 · 1:54:34 →An attorney for Thomes Creek Rock argued the five-year no-bid agreement exceeds the narrow emergency exception in Public Contract Code 22050 and asked the Board not to approve it.
Board of Supervisors — September 29, 2026 · 2:10:55 →The owner of Thomes Creek Rock said the gravel is worth about $3.8 million at his yard prices versus ~$300,000 in extraction costs, said no one contacted him for bidding, and called the deal a 'sweetheart deal.'
Board of Supervisors — September 29, 2026 · 2:18:18 →