California Record
Santa Clara
ApprovedOther

Laurelwood Junction Transmission Line Extension Project (CIP No. 2443)

Description

Extension of a 60 kV transmission line extension to serve a data center facility.

Impact summary

Extends electrical transmission lines to support commercial development with costs covered by the applicant.

Applicant

Name
Digital Realty

At a glance

Hearings
1
Public comments
0
Total mentions
1

Last vote · City Council

Approved7–0, unanimous

Last discussed Feb 10, 2026.