Winter 2023 storm road recovery continues
Summary
The county filed its seventh update on storm damage to roads; debt manager Jim Hamilton noted 12 road projects were completed this year using internal reserves instead of borrowing.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed May 19, 2026.
Impact analysis
A $5.65 million construction contract, with total project contract value capped at $6.2 million.
Residents of storm-damaged areas awaiting road repairs.
Mentions & discussions (2)
Board of Supervisors - May 19, 2026
The county filed its seventh update on storm damage to roads; debt manager Jim Hamilton noted 12 road projects were completed this year using internal reserves instead of borrowing.
Board of Supervisors - Feb 3, 2026
The county was set to award a $5.65 million construction contract to replace the Chimney Rock Road Bridge over Franklin Creek, with total contract value up to $6.2 million. The bridge project is funded through the county's roads capital program.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for San Luis Obispo County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.