Medium PriorityEnvironmentopen

Electric bus transition and charging infrastructure

Summary

Phase two of the transit yard charging build-out started March 2 and should finish March 27, supporting six delivered electric buses and two more in production. When fully built, the yard can charge 24 electric buses.

At a glance

Total mentions
3
Last 30 days
0

Last discussed Sep 9, 2026.