Wilderness Substation grounding transformers
Summary
Riverside Public Utilities was set to seek a roughly $3 million award for two 66kV grounding transformers at the Wilderness Substation. Keeping substation equipment current helps maintain reliable electric service.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Apr 13, 2026.
Impact analysis
About $3.04 million total from the electric capital account.
Electric customers across the Wilderness Substation service area benefit from reliable service.