High PriorityEnvironmentopen

Stalled battery storage and broken UOC solar array

Summary

The 36 MW battery storage project meant to help retire the aging Springs plant is stuck — no suitable site away from housing can be found — and the UOC solar carport array doesn't work. A council-approved spending plan included $5 million for solar/batteries at UOC/EOC, and staff committed to running an RFP after board pressure.

At a glance

Total mentions
1
Last 30 days
0

Discussed at 1 meeting in the last 60 days; most recently Sep 28, 2026.

Impact analysis

💰Financial impact

An estimated $60–75 million battery project and $5 million in planned solar/battery spending at UOC/EOC are affected.

✅Who benefits

Ratepayers if projects move forward and the aging Springs plant can be retired.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Riverside

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.