Hunter Substation 4kV-to-12kV conversion make-ready
Summary
$3.45 million to replace aging poles, transformers, and wire on the north side so Circuit 26 can switch to the higher 12kV voltage once Hunter Substation is rebuilt — commissioning starts early 2027 with full cutover by mid-2027.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Aug 24, 2026.
Impact analysis
$3,449,918.26 from the Electric Fund Major 4/12 KV Conversion Account.
Northside residents and businesses through improved reliability and capacity.