Summary

The city's three power plants need a five-year, $1.72 million emissions testing and environmental consulting contract with Onterris USA, a vendor that has served RPU for over 20 years and offers pricing well below market on key tests.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jul 13, 2026.

Impact analysis

💰Financial impact

Five-year contract totals $1,723,815, with estimated annual savings of over $100,000 versus market pricing and optimized test scheduling.

✅Who benefits

All electricity customers, through assured regulatory compliance and lower-than-market testing costs.