A 997-acre annexation and specific plan for up to 2,400+ homes, parks, and active-adult villages on farmland along the Stanislaus River. The commission recommended denial, but the City Council makes the final call.

At a glance

Total mentions
6
Last 30 days
0

Discussed at 1 meeting in the last 60 days; most recently Sep 22, 2026.

Impact analysis

💰Financial impact

The project would generate about $4 million in community benefit fees, $10 million in traffic fees, $4+ million in fire impact fees, and up to $2 million a year in general fund surplus per the applicant — while opponents warn of costly sewer expansion and rate increases.

✅Who benefits

Supporters say future homebuyers, aging residents seeking to downsize, and the city's general fund; opponents say only the developers profit.

⚠️Who could be affected

Opposing residents cite existing homeowners facing traffic, sewer rate increases, strained services, and the permanent loss of prime farmland and family farms.

Mentions & discussions (5)

MeetingSep 22, 2026

City Council / Local Redevelopment Authority - Sep 22, 2026

A 997-acre specific plan north of Patterson Road would add up to 2,682 homes across 18 villages, parks, trails and commercial space, and be pre-zoned for annexation. The council approved it 3-2 over broad opposition and a Planning Commission recommendation to deny.

MeetingSep 8, 2026

City Council / Local Redevelopment Authority - Sep 8, 2026

A Modesto resident urged the council to reject the proposed Riverwalk development, telling the council the developers have repeatedly overstated benefits — including that the 'river trail' actually sits on the land side of the levee, away from the river itself.

MeetingAug 4, 2026

Planning Commission - Aug 4, 2026

A 997-acre annexation and specific plan for up to 2,400+ homes, parks, and active-adult villages on farmland along the Stanislaus River. The commission recommended denial, but the City Council makes the final call.

MeetingJul 28, 2026approved

City Council / Local Redevelopment Authority - Jul 28, 2026

During public comment, resident Diego Hernandez argued a special planning commission hearing on the Riverwalk project is being used to grandfather the development before Measure M, and that Riverwalk isn't feasible without a new wastewater treatment facility the council has deferred. The dispute over the city's western expansion boundaries remains heated.

MeetingJul 21, 2026

Planning Commission - Jul 21, 2026

The commission will hold a special meeting on August 4 at the Community Center (not council chambers) to review the proposed Riverwalk project.

Related development

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Riverbank

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.