High PriorityRoadsopen

Roadway and storm drain construction scheduling

Summary

A sinkhole at Hawthorne and Indian Valley reopened and swallowed steel plates last week; Public Works got northbound lanes back open by Saturday and pumped out floodwater during a two-inch storm that briefly closed Palos Verdes Drive South.

At a glance

Total mentions
5
Last 30 days
2

Rising — discussed at 3 meetings since Sep 16, 2026, up from 0 in the two months before.

Impact analysis

💰Financial impact

An emergency contract was used and will come back to the Council for ratification.

✅Who benefits

Commuters on Hawthorne Boulevard and residents of the flood-prone Portuguese Bend area.

⚠️Who could be affected

Drivers, school commuters, and residents along PV Drive South and East will face months of lane closures, flagging operations, and construction noise.

Mentions & discussions (5)

MeetingOct 26, 2026approved

Meeting - Oct 26, 2026

Four funded projects — PV Drive South storm drains, PV Drive East road rehab, Western Avenue signals, and school crosswalks — are all reaching construction at once, right as a strong El Niño season begins. The staggered schedule aims to keep traffic moving but expect construction delays on the PV Drives through the holidays and beyond.

MeetingOct 20, 2026

City Council Meeting - Oct 20, 2026

Council members aired real frustration at the LA County engineer: water draining from Rolling Hills into Klondike and Paintbrush Canyons worsens the landslide, and years of talks haven't produced a fix. The council directed staff to keep pushing for county help — with El Niño days away.

MeetingSep 16, 2026

Infrastructure Management Advisory Committee (IMAC) - Sep 16, 2026

A record number of projects could all hit at once — Western Avenue, PV Drive South repaving, PV Drive East rehab — creating regional traffic snarls if not sequenced. Staff proposed a phased schedule to avoid overlapping closures and protect grant deadlines, and IMAC signed off.

MeetingMar 3, 2026

City Council Meeting - Mar 3, 2026

A deteriorating storm drain on northbound Crenshaw, about 830 feet north of Crest Road, was declared an emergency so repairs can be contracted without competitive bidding. $450,000 was shifted from the Montemalaga Canyon project to cover it.

MeetingFeb 17, 2026

City Council Meeting - Feb 17, 2026

A sinkhole at Hawthorne and Indian Valley reopened and swallowed steel plates last week; Public Works got northbound lanes back open by Saturday and pumped out floodwater during a two-inch storm that briefly closed Palos Verdes Drive South.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Rancho Palos Verdes

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.