Reservoir Tank Rehabilitation Progress
Summary
The 0.6 MG tank rehab is about 90% done — exterior and interior walls complete, flooring left — with completion expected around the end of June or July. Final change orders and payments are expected back before the board around August.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 5, 2026.
Impact analysis
Outstanding change orders (previously including a $40,000 tank coating inspection amendment) will come back to the board before final payment.
Water customers relying on the tank, which affects supply reliability during bypass mode.
Mentions & discussions (2)
City Council & Housing Authority Meeting (Closed Session 6PM / Regular Session 6:30PM) — October 5, 2026
The city is spending $167,475 plus a 10 percent contingency to slip-line six aging gravity sewer segments — preventive maintenance that reduces the risk of sewage backups and costly emergency repairs.
Port Hueneme Water Agency Meeting — June 15, 2026
The 0.6 MG tank rehab is about 90% done — exterior and interior walls complete, flooring left — with completion expected around the end of June or July. Final change orders and payments are expected back before the board around August.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Port Hueneme
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.