Street and sidewalk improvements
Summary
A written request for curb, gutter, and sidewalk on western Mariano Pines would cost roughly $500,000, and the street isn't on the city's improvement list — no short-term solution in sight.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 27, 2026.
Impact analysis
Roughly $500,000 estimated for about 3,000 feet of curb, gutter, and sidewalk.
Mariano Pines residents, especially pedestrians.
Mentions & discussions (2)
Traffic Safety Commission — October 27, 2026
A written request for curb, gutter, and sidewalk on western Mariano Pines would cost roughly $500,000, and the street isn't on the city's improvement list — no short-term solution in sight.
City Council Regular Meeting — February 4, 2026
The council funded street rehab on 19th and Alder Streets and the alley between 2nd and 4th (up to ~$1.03M) and new sidewalks on Prescott Lane (up to ~$173K).
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Pacific Grove
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.