Colorado Lagoon project delays
Summary
The long-running Colorado Lagoon project has drawn public frustration on social media, but staff say crews hit unexpected conditions when digging. The park is now targeted to open in summer or fall, with Public Works presenting an update at the Tidelands subcommittee meeting.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Jun 4, 2026.
Impact analysis
Cost overruns are part of the ordered report-back.
Residents will gain a reopened, improved lagoon park once work wraps up.
Nearby residents frustrated by the extended closure and construction timeline.
Mentions & discussions (2)
Marine Advisory Commission Executive Committee - Jun 4, 2026
The long-running Colorado Lagoon project has drawn public frustration on social media, but staff say crews hit unexpected conditions when digging. The park is now targeted to open in summer or fall, with Public Works presenting an update at the Tidelands subcommittee meeting.
City Council - Mar 24, 2026
The project is 39 months in — more than double the promised 18 — with two key streets closed and neighborhood traffic ballooning from hundreds to 2,500 cars a day on detour streets. The council ordered a 30-day report on what went wrong.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Long Beach
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.