High PriorityWater Utilitiesopen

Skedaddle Substation and transformer tariff

Summary

LMUD's new substation connecting to NV Energy is nearly built, but a Brazil-built transformer faces a $3 million federal tariff — about 10% of LMUD's annual budget. LMUD leaders are heading to Washington, D.C. to try to get relief.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Feb 10, 2026.

Impact analysis

💰Financial impact

A $3 million tariff against a roughly $30 million annual LMUD budget could pressure local electric rates.

✅Who benefits

LMUD customers who will gain a second power interconnection and better reliability.

⚠️Who could be affected

LMUD customers, if the tariff cost is ultimately passed into rates.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Lassen County

What the council decided, in plain English — one email a week.