Hackstaff Road crossing project delays
Summary
The Hat Creek Construction contract amendment was tabled a week because the original agreement date was misprinted and the contractor's schedule slipped — a familiar frustration on county road projects.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Mar 24, 2026.
Impact analysis
No new cost — the amendment only extends the completion date to August 31, 2026.
Residents near Hackstaff Road eventually get an improved rail crossing.
Residents waiting on the delayed project, as with Pine Town Road, face continued uncertainty.
Mentions & discussions (2)
Board of Supervisors — March 24, 2026
The Hackstaff Road public crossing improvement has slipped a year because of railroad and contractor scheduling. The Board extended the Hat Creek Construction contract 4-1, but Supervisor Neely pressed — unsuccessfully — for penalties and contractor accountability.
Board of Supervisors — March 17, 2026
The Hat Creek Construction contract amendment was tabled a week because the original agreement date was misprinted and the contractor's schedule slipped — a familiar frustration on county road projects.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Lassen County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.