City Hall and Library Project Change Orders
Summary
Four contracts and a change order for the new City Hall — audio-visual system, millwork, water/sewer connection, and server room fire suppression — totaling over $875,000 combined.
At a glance
- Total mentions
- 6
- Last 30 days
- 0
Last discussed May 26, 2026.
Impact analysis
Roughly $875,000 in combined approved contracts for the project.
City staff and residents using the new City Hall.
No groups negatively affected
Mentions & discussions (8)
Lake Elsinore's New $31.3M Civic Center Opening This Week In Historic Downtown
Lake Elsinore's New $31.3M Civic Center Opening This Week In Historic Downtown Patch
City Council
The council signed off on more contracts to finish the new City Hall — bathroom partitions and electrical systems — plus a construction agreement for Bid Set 'B' of the new library. The projects keep moving.
City Council
A contract with Edmondson Construction Co. for hardtop surfaces at the library site moves the long-awaited library project forward.
City Council
Big-ticket change orders moved forward for the new City Hall and Library projects — including $580,000 for City Hall windows and glazing, $199,000 for a library retaining wall, and added security and stormwater contracts. These capital projects shape downtown for decades.
City Council
The council quietly approved the mid-year budget update plus roughly $1.6 million in construction-related contracts, headlined by the $470,820 Hester Roofing deal for the new City Hall roof.
City Council
Four contracts and a change order for the new City Hall — audio-visual system, millwork, water/sewer connection, and server room fire suppression — totaling over $875,000 combined.
Lake Elsinore's New Library Breaks Ground, A New Chapter For Residents
Lake Elsinore's New Library Breaks Ground, A New Chapter For Residents Patch
Lake Elsinore New City Library Ground Breaking Planned
Lake Elsinore New City Library Ground Breaking Planned Patch
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Lake Elsinore
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.