Foothill Boulevard Street Remediation
Summary
The water district is worried: the 2019 fix was temporary, bids were rejected in April, and costs are climbing. New surveys show the ground isn't moving, and staff is exploring cheaper alternatives including video inspection of the buried pipe before October.
At a glance
- Total mentions
- 8
- Last 30 days
- 1
Discussed at 2 meetings in the last 60 days; most recently Nov 17, 2026.
Impact analysis
Rejected bids came in at $5.3 million versus a $1.6 million estimate, and every delay pushes costs higher.
Northwest La Cañada and Crescenta Valley water customers and Foothill Boulevard drivers once the permanent repair is done.
Continued delay risks a transmission main break, a water outage, and higher repair bills for taxpayers.
Mentions & discussions (8)
City Council (Regular) - Nov 17, 2026
The council is being asked to approve a change order of up to $28,135 for revised construction plans on the Foothill Boulevard street remediation project between El Camino Corto and Cypress Drive.
City Council (Regular) - Oct 6, 2026
The 2026 resurfacing project starts October 26 and runs about 50 working days; the council discussed scaling up to mass resurfacing and noted general fund spending on streets has more than doubled.
City Council (Regular) - Sep 15, 2026
Public Works reported major progress assessing the failed storm drain under Foothill Boulevard, with alternatives and costs under review — a recommendation is expected at the next meeting before the next storm season.
City Council (Regular) - Aug 4, 2026
The water district is worried: the 2019 fix was temporary, bids were rejected in April, and costs are climbing. New surveys show the ground isn't moving, and staff is exploring cheaper alternatives including video inspection of the buried pipe before October.
City Council Meeting - Budget Hearing - Jun 3, 2026
The city is spending $300,000 in special funds (Measure M, R, Prop C) to plan Foothill Boulevard's overhaul — surveying pavement and ADA gaps — because the road can't be repaved until accessibility issues are addressed.
City Council Meeting - Budget Hearing - May 21, 2026
Staff explained Foothill can't simply be repaved piecemeal because touching it triggers ADA compliance problems — it needs a full master plan. The council approved Hillard safety funding (non-general fund) given it's a key school feeder street, but wants foothill handled within the bigger streets strategy.
City Council Meeting - Budget Hearing - May 19, 2026
City Council Meeting - Budget Hearing - May 18, 2026
The RFP came back at about $5.6 million for phase one alone, but only $5.1 million is budgeted and the broken pipe isn't even included — the city admits it does not have enough money budgeted.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for La Cañada Flintridge
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.