Street Paving and Traffic Signal Funding
Summary
The Council was scheduled to award a construction contract for a new traffic signal at Baseline and Palmetto Avenues. A working signal there should improve safety for drivers crossing or turning at that busy intersection.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Last discussed Aug 11, 2026.
Impact analysis
About $1.09 million for construction, plus roughly $110,000 in contingency.
Motorists, pedestrians and nearby residents using the Baseline-Palmetto intersection.
Motorists may face temporary construction delays.
Mentions & discussions (4)
City Council Meeting — August 11, 2026
An $11 million construction contract was awarded to fix the long-troubled Etiwanda at Slover/Airport Drive intersection, with the City of Ontario covering about a third of the cost.
City Council Meeting — June 9, 2026
The Council was scheduled to award a construction contract for a new traffic signal at Baseline and Palmetto Avenues. A working signal there should improve safety for drivers crossing or turning at that busy intersection.
City Council Meeting — March 24, 2026
Two items addressed road infrastructure: a $31,194 Measure T-funded change order for a traffic signal at Duncan Canyon Road and Citrus Avenue, and a $300,000 contingency increase for the citywide pavement rehabilitation project.
City Council Meeting — February 24, 2026
The Council was set to award a construction contract for the FY 2025-26 citywide pavement rehabilitation project, funding street repairs across Fontana.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Fontana, California
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.