The city awarded the contract to finish the new public works Operations Complex at 3993 Broadway — foundation and interior build-out of the metal building that replaces the flood- and tsunami-zone corporation yard. The old corp yard site may become a Costco ground lease.

At a glance

Total mentions
5
Last 30 days
1

Discussed at 2 meetings in the last 60 days; most recently Nov 3, 2026.

Impact analysis

💰Financial impact

$6.07 million contract plus up to $908,975 contingency — $6.97 million total budget allocation.

✅Who benefits

Public works crews get a modern, disaster-resilient facility with better fleet maintenance capacity.

⚠️Who could be affected

None identified; potential contractor dispute with Swinerton remains unresolved.

Mentions & discussions (5)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Eureka

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.