Central Avenue / SR-60 Interchange Project Budget and Funding Reconciliation
Summary
The city finalized financial closeout for the Central Avenue and SR-60 Interchange project, transferring funds to correct prior accounting charges and securing maintenance agreements for landscaping and rock mulch.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Feb 3, 2026.
Impact analysis
Revises total project budget to $19,471,129 with city share at $17,387,776.
Motorists and regional commuters utilizing the improved interchange, as well as local taxpayers through accurate fund accounting.