Civic Issues
Topics getting the most attention in Burlingame public meetings, ranked by how frequently they are discussed.
2 issues in water utilities with medium priority
Donnelly and Alcazar water tanks rehabilitation
The council added $78,200 to the tank rehab contract to finish the job, bringing the total to $353,855. These tanks are part of the city's water storage system.
East Burlingame Terrace water main replacement
The city awarded a $2.37 million contract to Casey Construction to replace aging water mains in the East Burlingame Terrace subdivision, plus $423,016 for construction management. Better pipes mean fewer breaks and more reliable water service.