Rollins Road streetscape redesign
Summary
With the Broadway grade separation possibly never happening, Colson proposed studying a grade-separated bike/ped bridge over the Caltrain tracks near North Rollins Road to connect new housing to schools and Broadway. Colleagues agreed to explore it.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Jun 15, 2026.
Impact analysis
Not yet estimated; possible grant or SMCTA funding.
Residents of new Rollins Road housing, bicyclists, and students.
Mentions & discussions (3)
City Council — June 15, 2026
A $467,950 contract funds a quick-build traffic circle, bulb-outs, striping, and speed feedback signs on a high-injury corridor where speeding endangers kids. Final plans go to the Traffic Commission July 9; Stevenson floated future speed cameras if quick-builds don't slow drivers enough.
City Council — May 19, 2026
With the Broadway grade separation possibly never happening, Colson proposed studying a grade-separated bike/ped bridge over the Caltrain tracks near North Rollins Road to connect new housing to schools and Broadway. Colleagues agreed to explore it.
City Council — April 20, 2026
Rollins Road will get one travel lane each direction, a center median, offset parking, protected Class IV bike lanes, and continuous sidewalks — aiming for safer, calmer traffic. Construction runs spring through fall 2027.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Burlingame
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.